Project Company |
EA Solar Lampang Company Limited |
Location |
Muang District, Lampang Province |
Area |
Approximate 2,354 Rai |
PPA Contract Size |
90 MW |
Installed Capacity |
128.396 MW |
Status |
The project has achieved the Commercial Operation Date since 17 February 2015 |
Solar Cell Technology |
Poly Crystalline Solar Cell with Sun Tracking System |
Adder |
6.5 Baht per kWh, subsidiary period 10 years from COD |
BOI Tax Privileges |
Year 1 – 8 |
100% Tax exemption |
Year 9 – 13 |
50% Tax exemption |
|