Production capacity in each area of solar power plants.
Lampang
Phitsanulok
Nakhonsawan
Lopburi
Phatthananikom District, Lopburi Province
Capacity of
MW

Project Details
Project Company:
EA Solar Company Limited
Location:
Phatthananikom District, Lopburi Province
Area:
315 Rai
PPA Contract Size:
8 MW AC
Installed Capacity:
9.33 MW
Status:
The Project have achieved the Commercial Operation Date since 17 Oct 2012
Solar Cell Technology:
Poly Crystalline Solar Cell and Thin Film Solar Cell
Adder:
8.0 Baht per kWh, subsidiary period 10 years from COD
BOI Tax Privileges:
Year 1 – 8 : 100% Tax exemption
Year 9 – 13 : 50% Tax exemption
Remark:
A power purchase agreement (PPA) between 5 indirect subsidiary companies and the Electricity Generating Authority of Thailand (EGAT) for 5 years. Each default renewal is valid for 5 years under a condition that the party who wishes to renew the agreement must inform in writing to another party at least 30 days before the expiration date of the agreement.Takhi District, Nakhonsawan Province
Capacity of
MW

Project Details
Project Company:
EA Solar Nakornsawan Company Limited
Location:
Takhi District, Nakhonsawan Province
Area:
Approxiamte 1,852 Rai
PPA Contract Size:
90 MW AC
Installed Capacity:
126.126 MW
Status:
The Project has achieved the Commercial Operation Date since 23 December 2013
Solar Cell Technology:
Poly Crystalline Solar Cell
Adder:
6.5 Baht per kWh, subsidiary period 10 years from COD
BOI Tax Privileges:
Year 1 – 8 : 100% Tax exemption
Year 9 – 13 : 50% Tax exemption
Remark:
A power purchase agreement (PPA) between 5 indirect subsidiary companies and the Electricity Generating Authority of Thailand (EGAT) for 5 years. Each default renewal is valid for 5 years under a condition that the party who wishes to renew the agreement must inform in writing to another party at least 30 days before the expiration date of the agreement.Muang District, Lampang Province
Capacity of
MW

Project Details
Project Company:
EA Solar Lampang Company Limited
Location:
Muang District, Lampang Province
Area:
Approxiamte 2,354 Rai
PPA Contract Size:
90 MW AC
Installed Capacity:
128.396 MW
Status:
The Project has achieved the Commercial Operation Date since 17 Fubruary 2015
Solar Cell Technology:
Poly Crystalline Solar Cell with Sun Tracking System
Adder:
6.5 Baht per kWh, subsidiary period 10 years from COD
BOI Tax Privileges:
Year 1 – 8 : 100% Tax exemption
Year 9 – 13 : 50% Tax exemption
Remark:
A power purchase agreement (PPA) between 5 indirect subsidiary companies and the Electricity Generating Authority of Thailand (EGAT) for 5 years. Each default renewal is valid for 5 years under a condition that the party who wishes to renew the agreement must inform in writing to another party at least 30 days before the expiration date of the agreement.Prompiram District, Phisanulok Province
Capacity of
MW

Project Details
Project Company:
EA Solar Phisanulok Company Limited
Location:
Prompiram District, Phisanulok Province
Area:
Approximate 2,200 Rai
PPA Contract Size:
90 MW AC
Installed Capacity:
133.92 MW
Status:
The Project has achieved the Commercial Operation Date since 1 April 2016
Solar Cell Technology:
Poly Crystalline Solar Cell with Sun Tracking System
Adder:
6.5 Baht per kWh, subsidiary period 10 years from COD
BOI Tax Privileges:
Year 1 – 8 : 100% Tax exemption
Year 9 – 13 : 50% Tax exemption
Remark:
A power purchase agreement (PPA) between 5 indirect subsidiary companies and the Electricity Generating Authority of Thailand (EGAT) for 5 years. Each default renewal is valid for 5 years under a condition that the party who wishes to renew the agreement must inform in writing to another party at least 30 days before the expiration date of the agreement.